Clayton Street accessibility work in gear

The Clayton Street entrances to the Panhandle are undergoing a rebuild to improve accessibility, and signs posted on the site indicate the work will continue through September. Once the work is done and the grass grows back, most of us will probably take the yellow, accessible curb ramps for granted.

In May 2012, new curb ramps of this type were installed at Lyon Street. With this project and the curb work that came with the repavement of Stanyan in August 2012, the curb ramp infrastructure of the Panhandle is about a complete job with at least one major exception: Baker Street, across the street from Mercy Terrace, where most cyclists enter and exit the park. 

On each side, North and South of the park, a single crosswalk leads from the east side of Clayton Street to the Panhandle's pathways. The north path (approaching Clayton @ Fell Street) used to skirt alongside a large eucalyptus, but the tree was removed as a hazard in December. The north side job looks complicated, with digging, removal of roots and reconstruction of a stretch of curbside along the park.

Clayton @ Fell - some digging and removal of roots

Clayton @ Fell - re-build of the curb
The work on the south side of the park at Oak Street appears less complicated. However, this access point is important because it serves as an entry point for Park and Rec's vehicles that need to reach the dump.